OreGuard AI/ Mining Intelligence

Reporting & Audit

Actual vs planned blend performance and full change history for Gamsberg.

Avg deviation (Zn)
±0.18%

within tolerance

Tonnage adherence
97.4%

actual vs plan

Out-of-spec hours
3.5h

period total

Value uplift
+$112k

vs baseline

Planned vs Actual — Zn grade
Tonnage & Value Uplift
Deviation report
PeriodPlanned ZnActual ZnΔPlanned tActual tUplift
Day 17.12%7.03%-0.09%32,00031,567+$18,460
Day 26.91%6.77%-0.14%32,00033,296+$18,968
Day 36.97%6.86%-0.11%32,00033,274+$16,086
Day 47.24%7.1%-0.14%32,00032,181+$19,558
Day 57.47%7.39%-0.08%32,00031,435+$14,860
Day 67.45%7.47%+0.02%32,00031,766+$14,334
Day 77.2%7.03%-0.17%32,00031,836+$18,655
Change log / audit trail
TimestampUserActionEntityDetails
2026-05-27 06:02J. Pretorius (Planner)
approved
BP-2026-0527-ADay plan moved to executing
2026-05-26 18:30J. Pretorius (Planner)
created scenario
Contract X PriorityLocked SP-A1 = 13,000t
2026-05-26 17:30J. Pretorius (Planner)
created plan
BP-2026-0527-AObjective: maximise revenue
2026-05-26 19:10S. Mousavi (Planner)
created plan
BP-2026-0527-MObjective: minimise penalties
2026-05-27 04:18L. Naidoo (ROM Controller)
logged reclaim
SP-A11,200 t reclaimed to apron feeder